5000㎡ Steel Structure Factory Project Delivered in Oman1754548062425987.jpg

Requirement

A client from Angola approached us to design and supply a steel structure factory with dimensions of 102m × 45.3m, totaling over 5,000 square meters.

Unlike traditional single-structure workshops, this project was technically demanding, involving a combination of three structural systems:

  • Multi-span construction

  • Single-span construction

  • Additional/extension structures

Such complexity required careful structural planning and professional installation support. During the quotation stage, the client also shared a lower offer from another supplier and asked us to provide a more competitive price without sacrificing quality.

Solutions

To meet the client’s expectations and budget constraints, we proposed a hybrid structural solution, balancing both cost-efficiency and engineering integrity. The final plan included:

  • Simplified single-span structures for warehouse zones

  • Multi-span frames for large-scale production areas

  • Additional structures for auxiliary rooms or utility spaces

    1754548897959339.jpg

Material Strategy

We carefully selected materials to ensure durability, functionality, and ease of installation:

  • Main Frame: Q235B steel for beams and columns to ensure load-bearing stability

  • Walls: Brick walls were used only for ground-level reinforcement. The rest of the walls featured corrugated steel sheeting and EPS sandwich panels to optimize insulation and reduce cost

  • Roofing: Corrugated steel sheets paired with insulation material to enhance energy efficiency while keeping the structure lightweight for transport

Customizable Options

  • Structure Type: Single-span / Multi-span / Auxiliary structures

  • Panel Options: EPS / Rock wool / Glass wool / PU sandwich panels

  • Color Customization: RAL international color code options

  • Extra Features: Skylights, ventilators, solar panels, rainwater recycling

 Delivery & Support

Production Lead Time: 20–30 working days after final drawing confirmation

Shipping: Standard export packing suitable for 20ft/40ft containers

Installation Support:

  • Full structural and connection drawings

  • Step-by-step video installation guides

  • Remote or on-site technical support

  • Overseas installation team available upon request

Project TimeLine

1754549158450207.jpg
January 2024:We had our first interaction with the client from Oman, discussing their initial requirements for a steel structure factory. 
March 2024: 2024,The client provided the final detailed draft, which allowed us to proceed with accurate planning and further communication.
March 2024: After providing a formal quotation, both parties reached a mutual agreement and signed the contract.
Late March 2024: The client requested some modifications to the draft and quotation, which we promptly revised to meet their expectations.
April 2024: Production of the steel components officially began at our manufacturing facility.
May 2024: We started phased shipments of materials to Oman, ensuring secure packaging and on-time delivery.
July 2024: All components were successfully delivered to Oman, and we consulted with the client regarding technical support for installation.
August- October: Throughout the installation phase, we maintained close contact via WhatsApp, providing remote guidance, drawings, and video support to help ensure smooth progress.
Late October 2024: The 5,000+ sqm factory in Oman was successfully completed and fully assembled, marking a smooth and efficient collaboration.